A75 motorway renovation

  • Fayat Road Equipment
  • Mobility
  • Transport, Mobility

Two Breining Novalsealer 12000 units were used on the A75, south of Millau. The objective of the project was to repair the surface course of the motorway, on a moderately cracked road.

9 STAFF INVOLVED


A two-layer technique was used: a first layer with 0/6 aggregates, then a second with 0/10 aggregates). The team featured 9 staff including machine operators, but also logistics staff (loading and supplying of aggregates and emulsions). They produced up to 44,000m² per day with 2 machines running continuously.

breining-novasealer-on-the-a75-highway-millau-france.jpg
    44 000 per day
    2 machines
    9 staff involved