nh90-2-2.jpg

NH90 Helicopter service infrastructure in Pau

  • SEG-FAYAT
  • RAZEL-BEC
  • CASTEL & FROMAGET

Seg-Fayat (Fayat Group) won the design, construction and maintenance contract to build the NH90 helicopter service infrastructure on the site of the Pau-Uzein 5th Attack Helicopter Regiment.

Seg-Fayat (Fayat Group) won the design, construction and maintenance contract to build the NH90 helicopter service infrastructure on the site of the Pau-Uzein 5th Attack Helicopter Regiment. The 5th AHR is also engaged in all all sorts of domestic duties (MISSINT) such as providing natural disaster support (particularly floods and storms) and fire-fighting as part of the HÉPHAÏSTOS plan every summer in the south-east.

 

THIS PROJECT INCLUDES:

  • 1 maintenance building with 6 bays and connected workshops
  • 1 storage building with 13 bays and connected workshops
  • 1 battalion command building
  • Aeronautics platforms

This project is another fine example of group-wide synergies as the roads & utilities packages were won by Razel-Bec (sub-contractor) and the framework by Castel & Fromaget. It will begin in March 2019 and be delivered in September 2021.

 

nh90-2.jpg
    15 762 m² of floor area
    30 mois of work
    6 400 m² of concrete